Hi Mark,

You are quite right, this will be a tough run and will require quite 
some coordination. For that reason I think we should start joint 
T-474/T-480 meetings, possibly next week. Since we have a usual ESA 
Monday 8am/4pm meeting next week, maybe we can meet again at 
9:30am/5:30pm as usual or just stretch the ESA meeting a bit?

I guess the hardware crew will start a bit earlier, EU people arriving 
the weekend of June 7/8. Analysis guys should follow with a delay of a 
day or two. Then I suggest the following blocks:

June  9-11: Hardware installation, NMR calibrations, initial checkouts
June 11-13: Commissioning, goal: all BPM channels working, reasonable 
resolution, all calibration signals fed in, new movers working etc
June 14-15: Stability runs for BPM studies
June 16-20: Collimator + Energy spectrometer runs
June 21-22: Energy spectrometer stability studies + Collimator studies

Cheers,
Alex



Mark Slater wrote:
> Dear All,
> 
> Before Easter, Bino, Nigel and myself had a get-together to discuss  
> the upcoming run. We came up with the following list of things that need 
> to be done beforehand to ensure we have good BPM resolution and also some 
> specific T480/T474 things. Please add/remove as you see fit. Also, we will 
> probably be quite short-staffed for this run and so if anyone wants to 
> volunteer to be in charge of a specific area, do say so. I've 
> 'volunteered' some people already so please confirm if this is OK!
> 
> Thanks,
> 
> Mark
> 
> General BPM Jobs
> ----------------
> 
> Determine channel map (Yury?) 
> Setup scripts for processing, Data quality, Calibration (HH), Cal Tone 
> (Bino very kindly said he will set this up beforehand and I'll make sure 
> it's all working beforehand) 
> Check Cal tone running (Alex?) 
> Tune Cavities (Yury?) 
> Alignement Mover Systems (MikeW?)
> Interferometer (MikeH?)
> 
> 1 Shift to determine:
> 
> 	Frequency Run  (Freqs, decays, t0s, Bandwidth)
> 	Calibration
> 	Resolution/Stability
> 	Optimise Attenuation / Dynamic Range (maybe a bit optimistic)
> 	
> 
> T474
> ----
> 
> Take in situ Magnet Data
> Decide on fields/magnet running
> 
> 
> T480
> ----
> 
> ~2 shifts:
> 	Find edges of collimators
> 	Collimator surveys
> 	Optics (Frank isn't available so any help here would be 
> appreciated!)
> 	LOLA (Steve?)
> 
> 
> _______________________________________________
> esa-t474 mailing list
> esa-t474 at hep.ucl.ac.uk
> https://mail.hep.ucl.ac.uk/mailman/listinfo/esa-t474



More information about the esa-t474 mailing list