we're planning to mount BPM3-5 onto FFTB-style movers.
It would be great if you/bino could help integrate these into the T474
DAQ/control system, especially for use in the calibration procedure.
The SCP software already exists, but needs to be integrated into T474.

regards,
Johnny


On Tue, 27 Nov 2007, Alexey Lyapin wrote:

>
> Hi all,
>
> Bino and I were thinking about what needs to be done in the ESA before the 
> run in April, actually well before that run as there will surely be a lot of 
> things to do just before the run. As we may not have another high energy 
> operation period, we should be prepared.
> So, a draft plan for some work we think of doing in January/February next 
> year is below. Please, add anything you believe we missed!
>
> Best regards,
> Alex
>
>
> ESA - End Jan/Beginning Feb 2008 ???
> ************************************
>
> - one to two weeks
> - 2 people from UK
>  -> Bino, Stewart - if no clashes,
>     Alex - depending on visa/passport, Gary - ?
> - Michele, Sergey - if we plan to do some magnetic measurements
>
> - TODO
> ******
>
> 1. calibration tone system
>   ------------------------
>
>   - take calibration tone data over long periodes without beam
>     -> need to analyse the data maybe before !!!!
>
>
>   - upgrade/expand the system : upon availability of new components
>       -> need to order components a.s.a.p.
>       -> replace some of the amplifiers with higher power ones
>       -> revise the cabling - 1/4" cables to processors and from
>         calibration system, patch panels for BPM cables and couplers
>       -> think of a more efficient way of feeding the cal tone in
>       -> if needed, bring some of the cal system boxes back to UK
>
>   - need BPM system simulation finished for next run !
>
>   - more temperature sensors inside the processors.
>     -> do we have enough AI channels on the breakout box, or VSAM ?
>     -> more temp sensors ?
>
>
> 2. uk bpm mover system
>   -------------------
>
>   - integrate into SCP : o need ampl voltage which is high enough :
>                            check mover ADC specs !
>                            --> amplifier or other means of getting
>                                high enough VDC ?
>
>   - code in MINT to handle the ADC level as trigger for calibration
>     cycle : need to code the calibration routine in MINT
>
>   - setup macro which does the calibration with the ampls..
>
>   - test & setup the scripts to directly analyse the calibration runs
>
>
> 3. online monitoring
>   -----------------
>
>   - do we need new modern pc+screens for monitoring ?
>
>   - get some code up and running based on libbpm for online
>     monitoring... recycle mark's stuff ?, build new Qt interface ?
>
>
> 4. magnetic measurements ?
>   -----------------------
>
>   - need spectrometer simulation finished by next run
>
>   - do we want more measurements ? : talk to sergey, michele ?
>
>
> 5. zygo studies ?
>   --------------
>
> _______________________________________________
> esa-t474 mailing list
> esa-t474 at hep.ucl.ac.uk
> https://mail.hep.ucl.ac.uk/mailman/listinfo/esa-t474
>



More information about the esa-t474 mailing list