[esa-t474] ESA activities in Jan/Feb 2008
Alexey Lyapin
al at hep.ucl.ac.uk
Tue Nov 27 20:24:08 GMT 2007
Hi Mike,
I agree, we should have a t-474 meeting next week and discuss the visit,
system upgrades, and probably sign off on the NIM paper as well.
Cheers,
Alex
Woods, Michael B. wrote:
> Hi Alexey, thanks for the message. A 1-2 week visit ~Feb. 1 looks good. Would likely be good to have a phone meeting to discuss items in your list below. Perhaps next Monday? mike
>
> -----Original Message-----
> From: Alexey Lyapin [mailto:al at hep.ucl.ac.uk]
> Sent: Tuesday, November 27, 2007 4:13 AM
> To: esa-t474 at hep.ucl.ac.uk
> Subject: [esa-t474] ESA activities in Jan/Feb 2008
>
>
> Hi all,
>
> Bino and I were thinking about what needs to be done in the ESA before the run in April, actually well before that run as there will surely be a lot of things to do just before the run. As we may not have another high energy operation period, we should be prepared.
> So, a draft plan for some work we think of doing in January/February next year is below. Please, add anything you believe we missed!
>
> Best regards,
> Alex
>
>
> ESA - End Jan/Beginning Feb 2008 ???
> ************************************
>
> - one to two weeks
> - 2 people from UK
> -> Bino, Stewart - if no clashes,
> Alex - depending on visa/passport, Gary - ?
> - Michele, Sergey - if we plan to do some magnetic measurements
>
> - TODO
> ******
>
> 1. calibration tone system
> ------------------------
>
> - take calibration tone data over long periodes without beam
> -> need to analyse the data maybe before !!!!
>
>
> - upgrade/expand the system : upon availability of new components
> -> need to order components a.s.a.p.
> -> replace some of the amplifiers with higher power ones
> -> revise the cabling - 1/4" cables to processors and from
> calibration system, patch panels for BPM cables and couplers
> -> think of a more efficient way of feeding the cal tone in
> -> if needed, bring some of the cal system boxes back to UK
>
> - need BPM system simulation finished for next run !
>
> - more temperature sensors inside the processors.
> -> do we have enough AI channels on the breakout box, or VSAM ?
> -> more temp sensors ?
>
>
> 2. uk bpm mover system
> -------------------
>
> - integrate into SCP : o need ampl voltage which is high enough :
> check mover ADC specs !
> --> amplifier or other means of getting
> high enough VDC ?
>
> - code in MINT to handle the ADC level as trigger for calibration
> cycle : need to code the calibration routine in MINT
>
> - setup macro which does the calibration with the ampls..
>
> - test & setup the scripts to directly analyse the calibration runs
>
>
> 3. online monitoring
> -----------------
>
> - do we need new modern pc+screens for monitoring ?
>
> - get some code up and running based on libbpm for online
> monitoring... recycle mark's stuff ?, build new Qt interface ?
>
>
> 4. magnetic measurements ?
> -----------------------
>
> - need spectrometer simulation finished by next run
>
> - do we want more measurements ? : talk to sergey, michele ?
>
>
> 5. zygo studies ?
> --------------
>
> _______________________________________________
> esa-t474 mailing list
> esa-t474 at hep.ucl.ac.uk
> https://mail.hep.ucl.ac.uk/mailman/listinfo/esa-t474
More information about the esa-t474
mailing list