[esa-t474] [Fwd: Fwd: T-474 plan]
Bino Maiheu
bino at hep.ucl.ac.uk
Mon Mar 5 17:45:37 GMT 2007
-------- Forwarded Message --------
From: Yury Kolomensky <YGKolomensky at lbl.gov>
To: Bino Maiheu <bino at hep.ucl.ac.uk>
Cc: Yury Kolomensky <YGKolomensky at lbl.gov>, Stewart Boogert
<sboogert at pp.rhul.ac.uk>, Michael B. Woods <mwoods at slac.stanford.edu>,
Mike Hildreth <mikeh at omega.hep.nd.edu>, Krishna Kumar
<kkumar at physics.umass.edu>
Subject: Fwd: T-474 plan
Date: Mon, 5 Mar 2007 09:42:02 -0800
Hi Bino,
could you please forward this to T-474 list ? I guess we can have a
discussion of the plan first in two mins.
- BPM Calibration
(1) ESA BPM calibration with helmholz coils (A34 ?), run in dithering
mode (E158CALI): 3-point scan -20 G-m, 0, 20 G-m, 2-10 pulses at each
point (have to determine if this is compatible with feedback). Two
modes: long calibration (15 mins), 0.1% precision, and short
calibration (2 mins) -- <0.5%.
(2) Mover calibration (5 points, from -0.5 mm...0.5 mm, 10 sec/point),
2 BPMs
(3) Phase ramp run (energy part of E158DITH -- 3 points, +/- 0.5% if
possible, 2-10 pulses at each point, 2 mins).
Each setpoint on the coil, phase ramp, and mover would write a value to
a dedicated ADC channel.
So the sequence is:
Helmholz X (2-15 mins)
Helmholz Y (2-15 mins)
Phase Ramp (2 mins)
Mover X4 (2 mins)
Mover Y4 (2 mins)
(add X6/Y6 when it's installed)
Total: 40-60 mins (depending on efficiency). Repeat every 4 hours.
This does not define how we calibrate BPMs 28,31,32. I think we can use
well-calibrated BPMs in ESA and extrapolate upstream (with Q30/Q38
off). Occasionally (e.g. for T-480 or once per shift), should do
corrector A28/A29 scan with Q30/Q38 off (calibrate BPMs 31/32). Use
current BPMCali for this. This is to check that extrapolation from ESA
is reliable.
**** Action item: would like to check how extrapolation works early in
the run. Bino or Mark ?
- Spectrometer B-field scan: 3 pt scan (-B, 0, +B), 30 sec at each spot
(will have to look how quickly the magnets settle). Run once an hour on
polarity switch.
- Normal running sequence:
- Switch to -B
1) Long BPM Calibration (1 hour)
2) Run at -B (1 hour)
- Switch to 0 B
3) Short BPM Calibration (20 mins)
4) Run at 0 B (20 mins)
- Switch to +B
5) Short BPM Calibration (20 mins)
6) Run at +B (1 hour)
Total: 4 hours, repeat twice per shift.
Other issues:
1) Magnet standardization. Need Ray et al to define the procedure.
Standardize after every magnet trip
2) Magnetic field changes. Need Ray's input on this. I assume we are
always changing field from -B to +B, then all the way to -Bmax, and up
to -B. Need to define Bmax, ramp rate, etc and program into the magnet
control.
**** Action item: look at the existing magnet data to determine the
stability of B fields, ramp speed, etc. Bino ?
Any other issues ?
Yury
--
!!!!!
( o o )
@ -- Bino Maiheu, Dr. ;) ---------oOO----(_)----OOo------- @
/ :: WORK .:: / :: HOME .:: /
/ University College London / /
/ Physics and Astronomy / 31 Kilgour Road /
/ Gower Street / Forest Hill /
/ London WC1E 6BT / London SE23 1PG /
/ [tel] +44 20 7679 3454 / United Kingdom /
/ [fax] +44 20 7679 7145 / [mob] +44 7747 75 58 78 /
@ -------------------------------------------------------- @
More information about the esa-t474
mailing list